Large Structure Checklist

It’s the customer’s responsibility to check town requirements!

  • This is generally on average a 6-month process
  • Drawings, 1 month. Regular drawings take about 2-4 weeks and cost 500.00.   Sealed/stamped drawings cost 1000.00 and take 4-6 weeks
  • Township approval, 1-2 months. Once you have your drawings, please submit them to the town for Final approval.
  • Foundation, 1-2 months. We do not do the foundation but work with different companies based on your needs and location. Please ask for foundation contact information from your sales rep
  • Foundation is done, Build process 2-3 months. Once the foundation is done please contact us as we like to take final measurements to ensure a proper installation. Once the measurements are sent over, we should have a rough install date.
  • Please note, there is nothing we can do to expedite orders or drawings.
  • Drawings are a separate cost and an order for drawings needs to be in place to receive them.

 

Suggested Foundations

Check town requirements for foundation

Screen-Shot-2021-12-02-at-10.27.25-AM-300x254

Frost Protected Foundation

  • 8″ off of ground contact adding to the longevity 
  • Most towns will require this foundation

 

Screen-Shot-2021-12-02-at-10.27.07-AM-1024x119

Haunch Foundation

  • Simplest foundation to do
  • Some towns will allow this